Responses to Questions related to Clermont County Transportation Improvement District 03/31/08 Announcement requesting Letters of Interest (LOI).

Question Sent: Thu 4/3/2008 4:51 PM

  1. We noticed that Complex Lighting Design was listed as one of the ODOT Prequalification. Is lighting to be included along Clough Pike, for the length of the project or is lighting to be included only at the signalized intersection(s)?
  2. Are there any existing traffic counts available for this project?
  3. Has there been any analysis done at existing or proposed unsignalized intersections to determine if a signal is warranted?


Response:

  1. Lighting design will be included in the scoping of the selected firm.
  2. Available traffic counts will be provided during scoping of the selected firm.
  3. Traffic Signal Analysis will be included in the scoping of the selected firm.


Question Sent: Tue 4/15/2008 6:21 PM

The Stonelick - Williams Corner Rd Covered Bridge has a separate Design Scope of Services. However, I don't see a Design Scope of Services for the Clough Pike project. Is there a Scope of Services for the Clough Pike project or do I assume the LPA process covers it?

Response:

Scope of Services for the Clough Pike Widening project will be developed during scoping of the selected firm through the LPA process.

Question Sent: Wed 4/16/2008 3:57 PM

Reference PID # 83661 – CLE - Stonelick-Williams Corner Road Covered Bridge Rehabilitation Project, we are inquiring about the availability of the following documents:

  1. Recent inspection reports.
  2. Nomination documentation for the national registry of historic places.

Question: Is CCTID providing the environmental work (i.e., Level 1 CE, and Section 106 Review)? Or is it part of scope of work?

Response:

Recent inspection reports and other available relevant documents will be provided during scoping of the selected firm. As described in the Project Description, the Environmental Document will be by CCTID and not included in this scope.